Construction of Terephthalic (PTA)
Acid Production Facility for PKN ORLEN S.A.
Scope of works: workshop drawings, fabrication, delivery and erection of steel structure for new production facility. Quantity 1600 tons.
Realisation time: start September 2008,
finish: June 2010.
![]()
Improvements on S8 express way (
Trasa Armii Krajowej) - chainage 1+099,00km to 11+477,07km
Scope of works: fabrication, delivery and complex assembly of all steel structures for designed construction of road bridges on this express way in amount of 9, Total steel quantity: 3500 tons
Realisation time: April 2008,
finish: December 2010.
![]()
MARITZA EAST1, Power Station 2 x
300 MW
Scope of works: erection of boiler house standing part, erection of ducts. Quantity 5700 tons.;
Realisation time: October 2008,
finish: March 2010.
![]()
Bridge in Wrocław over Odra river
within the route of the A-8 speedway
Scope of works:delivery and erection of temporary support structure. Deliverty and erection of steel construction of Pylon for the execution of new bridge. Quantity 1500 tons,
Realisation time: start December 2008,
finish: September 2010.
![]()
Construction of the faculty of law
and administration Building of University of Adam Mickiewicz in Poznań
Scope of work: supply and erection work of educational building steel structure and lecture theatre, weight: 300 tones.
Realisation time: start May 2009,
finish: March 2010.
![]()
Bełchatów Power Plant -
858 MW Steam Power Unit.
Scope of work:erection work of the building Flue Gas Heat Recovery System, weight 650 tones.
Realisation time: start May 2009,
finish: March 2010.
![]()
Electrofilter for hard coal power
plant in Datteln, Germany.
Scope of work:fabrication and delivery of steel structure of electrofilter, weight: 1800 tones.
Realisation time: start May 2009,
finish: April 2010.
![]()
Electrofilters- Power Plant Hamm in
Germany.
Scope of work: mechanical erection of two electrofilters,
blocks D and E in Power Plant Hamm in Germany.
Quantity: 6.820 tones
Realisation time: start February 2010,
finish: march 2012.
![]()
Sewage-treatment Plant FORDON- part
2- ITPO Building.
Scope of works: delivery and erection of steel construction of ITPO building with anticorrosion protection, weight 250 tones.
Realisation time: start September 2009,
finish: December 2010.
![]()
Construction of the Express Road
S-2, section Konotopa- Puławska with the construction of connector with
Airport Okęcie and Marynarska street ( S-79) in Warsaw.
Scope of work: prefabrication, delivery and erection work of steel construction of four objects for road junction “ Okęcie” in amount of approximately 570 tons.
Realisation time: start October 2009,
finish: September 2010.
![]()
Construction of multifunctional
Stadium In Wroclaw.
Scope of work: prefabrication, delivery and erection works of roof steel construction and facade of stadium in amount of approximately 4000 tones.
Realisation time: start October 2009,
finish: September 2010.
![]()
Improvements on S5 express way, line Gniezno- Poznań,
Section 1: Gniezno- Czachurki - chainage km- (0+420)to km 14+475, length: 14,9 km.
Scope of work: Delivery and erecetion works od the Viaduct WN- 24; km 27+925,00 .
Realisation time: start December 2009,
finish: December 2010.