Construction of Terephthalic (PTA) Acid Production Facility for PKN ORLEN S.A.

Scope of works: workshop drawings, fabrication, delivery and erection of steel structure for new production facility. Quantity 1600 tons.
Realisation time: start September 2008,
finish: June 2010.


Improvements on S8 express way ( Trasa Armii Krajowej) - chainage 1+099,00km to 11+477,07km

Scope of works: fabrication, delivery and complex assembly of all steel structures for designed construction of road bridges on this express way in amount of 9, Total steel quantity: 3500 tons
Realisation time: April 2008,
finish: December 2010.


MARITZA EAST1, Power Station 2 x 300 MW

Scope of works: erection of boiler house standing part, erection of ducts. Quantity 5700 tons.;
Realisation time: October 2008,
finish: March 2010.


Bridge in Wrocław over Odra river within the route of the A-8 speedway

Scope of works:delivery and erection of temporary support structure. Deliverty and erection of steel construction of Pylon for the execution of new bridge. Quantity 1500 tons,
Realisation time: start December 2008,
finish: September 2010.


Construction of the faculty of law and administration Building of University of Adam Mickiewicz in Poznań

Scope of work: supply and erection work of educational building steel structure and lecture theatre, weight: 300 tones.
Realisation time: start May 2009,
finish: March 2010.


Bełchatów Power Plant - 858 MW Steam Power Unit.

Scope of work:erection work of the building Flue Gas Heat Recovery System, weight 650 tones.
Realisation time: start May 2009,
finish: March 2010.


Electrofilter for hard coal power plant in Datteln, Germany.

Scope of work:fabrication and delivery of steel structure of electrofilter, weight: 1800 tones.
Realisation time: start May 2009,
finish: April 2010.


Electrofilters- Power Plant Hamm in Germany.

Scope of work: mechanical erection of two electrofilters,
blocks D and E in Power Plant Hamm in Germany.
Quantity: 6.820 tones
Realisation time: start February 2010,
finish: march 2012.


Sewage-treatment Plant FORDON- part 2- ITPO Building.

Scope of works: delivery and erection of steel construction of ITPO building with anticorrosion protection, weight 250 tones.
Realisation time: start September 2009,
finish: December 2010.


Construction of the Express Road S-2, section Konotopa- Puławska with the construction of connector with Airport Okęcie and Marynarska street ( S-79) in Warsaw.

Scope of work: prefabrication, delivery and erection work of steel construction of four objects for road junction “ Okęcie” in amount of approximately 570 tons.
Realisation time: start October 2009,
finish: September 2010.


Construction of multifunctional Stadium In Wroclaw.

Scope of work: prefabrication, delivery and erection works of roof steel construction and facade of stadium in amount of approximately 4000 tones.
Realisation time: start October 2009,
finish: September 2010.


Improvements on S5 express way, line Gniezno- Poznań,
Section 1: Gniezno- Czachurki - chainage km- (0+420)to km 14+475, length: 14,9 km.

Scope of work: Delivery and erecetion works od the Viaduct WN- 24; km 27+925,00 .
Realisation time: start December 2009,
finish: December 2010.