Eco-friendly

Power Station 2×800 MW Eemshaven, Netherlands

Scope of works: erection of main steel structure of boiler, boiler house, bunker house with bunker and platforms with delivery and erection of secondary steel structure. Gradual lifting of ducts. Quantity for each block: over 8000 tons.
Realisation time: start June 2010,
finish December 2013.