Building a Footbridge over the Bug River

Contract value: 8,961,988.15 PLN gross
Completion date: October 2025

Contract Conclusion

On May 8, 2024, Mostostal Kielce S.A. ("Contractor") – a subsidiary of Mostostal Warszawa S.A. (holding 100% of the Contractor's share capital) signed a contract with the County and Municipal Association "Nad Bugiem" ("Principal") for the implementation of the task "Construction of a footbridge over the Bug River" in the design and build formula.

Contractual Details

  • Gross contract value: PLN 8,961,988.15
  • Contract completion deadline: 17 months
  • Payment deadline: 35 days
  • Warranty period: 108 months
  • Security for due performance: 5% of the gross remuneration value in the form of a bank guarantee

Investment Information

The construction of a footbridge over the Bug River is a joint investment of three local governments - the municipalities of Drohiczyn and Korczew, and the Siemiatycze County, which have established the County and Municipal Association "Nad Bugiem" for its implementation.

The footbridge will connect Drohiczyn with Bużyska. Until now, crossing the river at this point has been possible during the summer season using a ferry, which is used by pedestrians, cyclists, and of course, drivers. The planned footbridge will serve pedestrians and cyclists and will significantly enhance the tourist attractions of the town. This project aligns with the efforts to develop transportation infrastructure and promote the tourist attractions of the Bug River.

The investment will be financed by a grant obtained from the government's Poland 2030 program, with co-financing from the local governments involved in this task.

The completion of the investment is planned for October 2025.