Works on the E 65 line on the section Będzin – Katowice Szopienice Płd. – Katowice – Katowice Piotrowice
Completion date:
August 2025
Scope of work: comprehensive assembly of steel structures of viaducts WK-3, WK-9.1, WK-10, WK-21, WK-22.
Realization time:
start: January 2025,
finish: August 2025.