B100 BW 0054 Reconstruction of the bridge over the Mulde river near Pouch, Germany
Deadline for completion: August 2027
Scope of work: general contractor for the reconstruction of a 2660-tons steel bridge on the B100 road near Pouch, Germany.
Realisation time: start June 2025,
finish: August 2027.
Contract Value: PLN 19,920,086.53 gross
Deadline for completion: April 4, 2027
Contract Value: PLN 38,553,667.89 gross
Deadline for completion: September 22, 2027
Deadline for completion: November 2026
Deadline for completion: July 2025
Deadline for completion: August 2025
Deadline for completion: December 2026
Deadline for completion: June 2030
Deadline for completion: August 2027
Deadline for completion: March 2025
Podkarpackie Voivodeship Office in Rzeszów