Infrastructural construction
Expansion of the county road No 1405R Zarzecze – Siedliska consisting in the demolition of the existing bridge and construction of a new bridge over the river Wislok with access roads and the necessary facilities
Scope of work: general implementation of the investment consisting in demolition of the existing bridge and construction of a new bridge over the river Wislok in km 1 + 419 with the access roads section from km 1 + 040 to km 1 + 500 and the necessary technical facilities, buildings and equipment.
Realisation time: start August 2018,
finish: March 2019.
Contract Value: PLN 19,920,086.53 gross
Deadline for completion: April 4, 2027
Contract Value: PLN 38,553,667.89 gross
Deadline for completion: September 22, 2027
Deadline for completion: June 2030
Deadline for completion: August 2027
Deadline for completion: December 2024
Deadline for completion: December 2024
Fachstelle Brücken Mitte beim Wasserstraßen-Neubauamt Helmstedt