Works on the railway line No. 35 section Ostrołęka Chorzele
Deadline for completion: 20 months
Scope of work: demolition of the old bridge, fabrication, delivery and erection of a new bridge over the river Narew in amount of approximately 970t.
Realisation time: start August 2020.
Finish: March 2022.
Contract Value: PLN 19,920,086.53 gross